Construction Updates

March 2024

  • Pile driving has progressed.
  • Solar panel installation continues.
  • Substation work is 90% completed.
  • Grading work throughout the site is progressing.
  • Site continues to implement environmental protection activities.

February 2024

  • Pile driving has progressed.
  • Solar panel installation continues.
  • Substation work is on going.
  • Grading work throughout the site is progressing.
  • Site continues to implement environmental protection activities.

November 2023

Substation / Switchyard / Laydown Yard

  • Installation of Switchyard and Substation Pad – 100%
  • Switchyard work has progressed
  • Substation work approximately 60% completed.
  • Laydown Yard / Office Parking Lot – Trailers installed
  • 2 Proposed site access roads – 100%

Photo: Switchyard & Basins (Photo Taken: September 2023)

Phase 1 – 50 MW (Construction scheduled to start May 2023)

  • Tree Clearing – 100%
  • Grading Complete
  • SWPPP BMPs (including basins) Installed – 100%
  • 1 Proposed site access road – 100%
  • Main component work:
    • Racking and pile installation – 0%
    • Electrical components installation – 0%
    • Module installation – 0%
    • Etc.
  • Delivery of racking, modules and electrical components continues.
  • Contractor continues civil and  environmental protection work. This work will be on-going.