Construction Updates
March 2024
- Pile driving has progressed.
- Solar panel installation continues.
- Substation work is 90% completed.
- Grading work throughout the site is progressing.
- Site continues to implement environmental protection activities.
February 2024
- Pile driving has progressed.
- Solar panel installation continues.
- Substation work is on going.
- Grading work throughout the site is progressing.
- Site continues to implement environmental protection activities.
November 2023
Substation / Switchyard / Laydown Yard
- Installation of Switchyard and Substation Pad – 100%
- Switchyard work has progressed
- Substation work approximately 60% completed.
- Laydown Yard / Office Parking Lot – Trailers installed
- 2 Proposed site access roads – 100%
Photo: Switchyard & Basins (Photo Taken: September 2023)
Phase 1 – 50 MW (Construction scheduled to start May 2023)
- Tree Clearing – 100%
- Grading Complete
- SWPPP BMPs (including basins) Installed – 100%
- 1 Proposed site access road – 100%
- Main component work:
- Racking and pile installation – 0%
- Electrical components installation – 0%
- Module installation – 0%
- Etc.
- Delivery of racking, modules and electrical components continues.
- Contractor continues civil and environmental protection work. This work will be on-going.